IAL Decision 1 Practice Paper 2: Aiming for A
8 questions • 75 marks • 1 hour 30 minutes • calculator allowed • answer-book pages • mark scheme • worked solutions
About this paper
This IAL Decision 1 practice paper is the second of three and is set above a typical real WDM11 series. Most of its eight questions pass a result from one algorithm into another: final values from Dijkstra's algorithm decide the pairings in a route inspection, and a spanning tree gives a lower bound for a travelling salesman route that contains an unknown distance.
Nothing is printed for you to aim at, and several parts ask for a range or a set of values instead of a single answer. You will work backwards from a packing to the length of a box, from a nearest neighbour route to a condition on x, and from an objective to the range of a coefficient.
Every answer-book page follows its question, including a blank space for drawing an activity network. The mark scheme marks each link between chapters, and the worked solutions complete every page in red pen.
Is this the right paper for you?
This paper is for students working towards grade A in D1, and for anyone who found Paper 1 manageable. Its difficulty comes from the joins, such as reading a shortest distance from Dijkstra's algorithm and using it in a route inspection two parts later.
If the single-chapter questions still cost you marks, sit Decision 1 Practice Paper 1 first. When this paper goes well, try Decision 1 Practice Paper 3.
Rough grade guide: A 53 • B 46 • C 39 out of 75, a few marks below recent WDM11 grade boundaries because this paper is harder.
The questions
- Question 1 (7 marks): A flow chart traced with exact fractions until two values agree, the purpose of the algorithm, and the output from a negative start. Practise it: Chapter 1: Algorithms.
- Question 2 (8 marks): Lengths of wood: a quick sort into descending order, first-fit decreasing, and the possible box lengths from how one box was filled. Practise it: Chapter 1: Algorithms.
- Question 3 (9 marks): A distance matrix: Prim's algorithm, the tree drawn, the lengths of a new road that would change the tree, and the degrees of the vertices. Practise it: Chapter 3: Algorithms on Graphs, Chapter 2: Graphs and Networks.
- Question 4 (10 marks): Cycle paths: Dijkstra's algorithm from A, then a route inspection that uses its final values, then the best two points to start and finish. Practise it: Chapter 3: Algorithms on Graphs, Chapter 4: Route Inspection.
- Question 5 (10 marks): A table of least distances with an unknown x: a condition from the nearest neighbour route, both bounds in terms of x, and a range for x. Practise it: Chapter 5: The Travelling Salesman Problem, Chapter 3: Algorithms on Graphs.
- Question 6 (8 marks): A precedence table drawn as an activity network with exactly two dummies, and the reason each dummy is needed. Practise it: Chapter 6: Critical Path Analysis.
- Question 7 (12 marks): Event times, a cascade chart and a lower bound for workers, then a schedule for that number of workers and the time it takes. Practise it: Chapter 6: Critical Path Analysis.
- Question 8 (11 marks): A farm: constraints from a percentage and a ratio, the feasible region, the best whole-number plan and the range for one profit. Practise it: Chapter 7: Linear Programming.
Worked example
Question 8(c) asks a farmer, planting whole numbers of hectares, to maximise a profit of 300x + 200y. The objective line leaves the feasible region where x + y = 60 meets 5x + 2y = 200, at a point with fractional coordinates, 26⅔ and 33⅓.
Rounding to the nearest whole numbers gives (27, 33), but that needs 201 units of fertiliser when only 200 are available. Checking the whole-number points around the vertex shows that (26, 34) is the best feasible plan, with a profit of £14 600.

Where marks are lost
- Ignoring a piece that did not fit, Question 2(c). The 14 cm piece was left out of the first box, so 35 + 14 = 49 is more than L, which limits L to 47 or 48.
- Comparing the new road with the wrong arc, Question 3(c). The new road AC replaces the longest arc on the tree path from A to C, which is BG at 15 km.
- Using the direct arc AB, Question 4(b). Dijkstra's algorithm already gives the shortest A to B distance as 16 km by A, C, B, so the pairing totals 37, not 38.
- Dropping a condition from an earlier part, Question 5(d). The bounds give 25 ≤ x ≤ 30, but the lower bound in (c) only holds for x < 28, so the range is 25 ≤ x < 28.
- Trusting the worker bound, Question 7(e). Three workers is the lower bound, but no arrangement of three finishes in 20 days; the best schedule takes 21.
Common questions
How should I lay out Dijkstra's algorithm?
Fill in every box: the order of labelling, the final value and each working value in the order you found it. A missing working value loses an accuracy mark.
When is a dummy needed in an activity network?
When one activity depends on only some of the activities that another depends on, or when two activities would share the same start and end events.
What if the optimal vertex is not a whole number?
Test the whole-number points around it against every constraint, and compare their values of the objective; the nearest point may not be feasible.