IAL Decision 1: Critical Path Analysis Exam Questions

10 exam-style questions · 80 marks · about 96 minutes · full mark scheme

Specification: D1 Critical path analysis

Quick Links

About this chapter

Critical path analysis plans a project made of activities that depend on one another. You draw the activity network, find the earliest and latest times for each event, identify the critical activities, and then schedule workers. The January 2025 examiners reported networks much better drawn than in previous series, but still saw arrows hidden at the nodes and diagrams too small to read.

This chapter covers drawing networks with activity on arc, dummies, early and late event times, critical activities, total float, cascade charts, activities happening at a given time, and the number of workers. The later questions include two critical paths, a delayed activity, and an activity whose duration is an unknown x.

The ten questions

  • Q1 (6 marks): an activity network drawn from a precedence table with the fewest dummies.
  • Q2 (6 marks): early and late event times, the critical activities and the minimum completion time.
  • Q3 (6 marks): the float of three activities from given event times, the critical path, and a 3-hour delay.
  • Q4 (6 marks): a cascade chart from a table, then the activities that must be happening at 7.5 days.
  • Q5 (6 marks): a precedence table read from a network, and why each of its two dummies is needed.
  • Q6 (10 marks): a network with exactly five dummies, its event times and the critical activities.
  • Q7 (10 marks): why a dummy is needed, event times, the critical path, a float, and a lower bound for workers.
  • Q8 (10 marks): floats showing two critical paths, a cascade chart, and the activities during day 13.
  • Q9 (10 marks): a lower bound for workers, a schedule that meets it, and the effect of one activity overrunning.
  • Q10 (10 marks): an activity of x hours: event times, the values of x that make it critical, and its float.

Key skills tested

Drawing networks. Use activity on arc: each activity is an arrow between events. Draw large, with arrows in the middle of each arc and a single start and finish.

Dummies. A dummy is a dotted arrow of zero duration. It shows a dependency, or keeps two activities from sharing the same start and end events.

Early event times. Work forwards from 0. Where arrows meet, take the largest of the incoming totals.

Late event times. Work backwards from the finish. Where arrows leave, take the smallest of the outgoing values.

Critical activities. An activity is critical when its start and end events have equal early and late times and its duration fills the gap.

Total float. Late finish − early start − duration. Critical activities have zero float.

Cascade charts. Draw each activity as a bar from its earliest start, with its float shaded after it. Use a ruler.

At a given time. An activity must be happening when even its latest possible start and earliest possible finish include that time.

Workers. A lower bound is the total of all durations divided by the critical time, rounded up. It may not be achievable, so test it with a schedule.

Key skills page for IAL Decision 1 Chapter 6, Critical Path Analysis: nine skill cards from drawing networks to workers, with a skills map

Worked example

Question 3 from this chapter. An activity network shows early and late event times. (a) Find the total float of C, F and I. (b) State the critical path. (c) C is delayed by 3 hours. Explain the effect.

(a) Total float = late finish − early start − duration. C: 6 − 0 − 4 = 2. F: 18 − 6 − 8 = 4. I: 15 − 4 − 7 = 4.

(b) B–H–K.

(c) C has only 2 hours of float, less than the 3-hour delay, so the project is delayed by 1 hour, to 23 hours.

A delay up to the float costs nothing; only the excess delays the whole project.

Worked solution to Decision 1 Chapter 6 Question 3: C has float 2 and F and I have float 4, the critical path is B–H–K, and a 3-hour delay to C delays the project by 1 hour

Seen on real papers
Every question in our booklets is original. These are the recent papers where each question type has appeared.

  • January 2025, Q4 and Q7: a network needing a dummy for uniqueness, then event times, critical activities, a float, a cascade chart and the activities during one day, as in Q1, Q5, Q7 and Q8.
  • June 2023, Q1 and Q5: early and late times, a float, a lower bound and a four-worker schedule, then an activity network, as in Q2, Q6 and Q9.
  • October 2021, Q4: a precedence table, event times, a lower bound for workers and a schedule, as in Q5 and Q9.

Where marks are lost

  • The wrong kind of network. In June 2023 the small minority who drew activity on node lost all five marks; January 2025 saw the same.
  • Arrows and dummies. Both reports saw arrows drawn at the ends of arcs, hidden by the nodes, and superfluous dummies or no single finish.
  • Late times. In January 2025 the late times at the ends of A and C were often larger than the one at B, which lost both marks for those boxes.
  • Too few workers. In June 2023 the modal mark for the schedule was 1 out of 3, as many tried to use just three workers to match their lower bound.

Common questions

Why are dummies needed?
Either to show that one activity depends on another without adding time, or to stop two activities sharing the same start and end events.

How do I find total float?
Subtract the early start and the duration from the late finish. Zero float means the activity is critical.

Is the lower bound for workers always enough?
No. It assumes no gaps; a schedule may need more, so draw one to check.